Board Member 
Reports on Liberty Center Status as of February 25, 
2016
by
Jim 
Mayfield
Sun City Anthem Board Director 
Since the 
report on Liberty Center was issued in January, the professional engineering 
firm retained by the Board submitted its assessment report on the roof and 
interior defects at Liberty Center.  The report documents interior and roof 
issues at Liberty Center that, in its professional opinion, are related to 
construction defects, deficient maintenance procedures, and normal wear and 
tear.
In order to 
minimize the financial cost of necessary repairs to the Members, the Board 
initiated two actions to recover the cost of repairing the 
damages.  
First, SCA filed an insurance claim for repair of damages 
that it believes are insured losses. 
Second, the Board continued its consultations with 
attorneys to determine if SCA has legal actions it may take to recover the costs 
to repair the damages at Liberty Center from a 
third-party.
As reported 
by the President, the Board has retained special counsel to 
initiate a construction defect cost recovery process under Chapter 40 of Nevada 
law. 
The urgency 
to file this action was a result of changes to Chapter 40 during the recent 
legislative session.  
Specifically, the revised Chapter 40 
requires that only claims filed before February 24, 2016 will be interrupted 
under the terms of the less restrictive conditions under Chapter 40 that existed 
before the recent legislative 
changes.
The first 
step in the construction defect cost recovery legal process requires SCA to 
provide the developer notice of the alleged construction defects and provide the 
developer up to 90 days to independently assess the damages and agree to assume 
responsibility for correcting the defects.  
Accordingly, 
all repair work to correct problems at the Liberty Center has been halted.  
If the 
developer notifies SCA that it will not voluntarily assume responsibility to 
correct the defects or after 90 days, SCA may resume work to correct the 
defects. 
The estimated time needed to compete the interior and roof repairs 
is 10 weeks.  
Therefore 
for planning purposes, residents should plan for Liberty 
Center, including the outdoor pool area, to be out of service through August 
2016.
Special 
counsel has reviewed the assessment report of the professional engineering firm 
mentioned above.  Special counsel advised the Board that the assessment report 
is now a work product pursuant to the Chapter 40 action.  
Accordingly, 
the report is a confidential attorney-client work product and will not be 
available for public disclosure at this time. 
Cost paid to 
date is $51,843.44.  
This amount 
does not reflect actual cost incurred to date since work has been performed for 
which contractors have not submitted invoices approved for payment. 
I shall 
provide an undated report in March.  
After March, 
control of the project and reports on Liberty Center will be the responsibility 
of the SCA General Manager.
 
 